John D. Spreckels Lawn Bowling Green Storm Related Turf Replacement

Share John D. Spreckels Lawn Bowling Green Storm Related Turf Replacement on Facebook Share John D. Spreckels Lawn Bowling Green Storm Related Turf Replacement on Twitter Share John D. Spreckels Lawn Bowling Green Storm Related Turf Replacement on Linkedin Email John D. Spreckels Lawn Bowling Green Storm Related Turf Replacement link

At a Glance

Following the severe rain event on January 22, 2024, the John D. Spreckels Center's Lawn Bowling Green turf was damaged. The replacement of the damaged turf was eligible for reimbursement under the City of Coronado's insurance policy and the City Council approved moving forward with the turf replacement under the City’s insurance policy on September 17, 2024.


Scope of Work

  • Work will focus only on the removal of the existing turf and the replacement of the turf on the Lawn Bowling Green with a like-kind-quality turf.
  • Plans for root barriers and a drainage pump system have been removed from the scope of work.


Construction Schedule (updated)

Project materials were ordered immediately after Council approval and the product arrived in San Diego on January 8, 2025. With favorable weather conditions and no unexpected issues at the jobsite, the project is currently ahead of schedule. The Contractor anticipates completion during the week of February 10th.

Construction Start Onsite
January 15, 2025
Estimated Project Duration
(including contingencies for unexpected issues)
72 working days
Estimated Construction Completion
April 28, 2025
Updated Construction Completion February 12, 2025



Construction Progress February 5, 2025


Construction Progress February 5, 2025


Construction Progress January 30, 2025

Lawn Bowling Green before January 22, 2024


Lawn Bowling Green flooded on January 22, 2024



At a Glance

Following the severe rain event on January 22, 2024, the John D. Spreckels Center's Lawn Bowling Green turf was damaged. The replacement of the damaged turf was eligible for reimbursement under the City of Coronado's insurance policy and the City Council approved moving forward with the turf replacement under the City’s insurance policy on September 17, 2024.


Scope of Work

  • Work will focus only on the removal of the existing turf and the replacement of the turf on the Lawn Bowling Green with a like-kind-quality turf.
  • Plans for root barriers and a drainage pump system have been removed from the scope of work.


Construction Schedule (updated)

Project materials were ordered immediately after Council approval and the product arrived in San Diego on January 8, 2025. With favorable weather conditions and no unexpected issues at the jobsite, the project is currently ahead of schedule. The Contractor anticipates completion during the week of February 10th.

Construction Start Onsite
January 15, 2025
Estimated Project Duration
(including contingencies for unexpected issues)
72 working days
Estimated Construction Completion
April 28, 2025
Updated Construction Completion February 12, 2025



Construction Progress February 5, 2025


Construction Progress February 5, 2025


Construction Progress January 30, 2025

Lawn Bowling Green before January 22, 2024


Lawn Bowling Green flooded on January 22, 2024



Page last updated: 05 Feb 2025, 03:13 PM