Progress Update April 3, 2024
The project is in its eighth week of construction and work is progressing.
- Recreations Pool's waterline tiles are being installed;
 - Competition Pool’s Lane line tile mortar beds are being installed;
 - New in-pool lighting conduits have been installed;
 - Soil remediation continues in preparation for the new concrete deck.
 
Waterline Tile Installation

New Lighting Conduit

Lane Line Tile Mortar Beds

Soil Remediation Equipment