Progress Update April 3, 2024
The project is in its eighth week of construction and work is progressing.
- Recreations Pool's waterline tiles are being installed;
- Competition Pool’s Lane line tile mortar beds are being installed;
- New in-pool lighting conduits have been installed;
- Soil remediation continues in preparation for the new concrete deck.
Waterline Tile Installation
New Lighting Conduit
Lane Line Tile Mortar Beds
Soil Remediation Equipment
Share Progress Update April 3, 2024 on Facebook
Share Progress Update April 3, 2024 on Twitter
Share Progress Update April 3, 2024 on Linkedin
Email Progress Update April 3, 2024 link
