Progress Update April 3, 2024

The project is in its eighth week of construction and work is progressing.

  • Recreations Pool's waterline tiles are being installed;
  • Competition Pool’s Lane line tile mortar beds are being installed;
  • New in-pool lighting conduits have been installed;
  • Soil remediation continues in preparation for the new concrete deck.

Waterline Tile Installation


New Lighting Conduit

Lane Line Tile Mortar Beds


Soil Remediation Equipment