Share Free Grand Reopening Pool Party - Olympics Style on Facebook
Share Free Grand Reopening Pool Party - Olympics Style on Linkedin
Email Free Grand Reopening Pool Party - Olympics Style link
Final touches to the Aquatics Center pools are finishing up the week of August 12, 2024. The Aquatics Center is celebrating the reopening of the pool on Saturday, August 17 with a FREE grand reopening pool party. Aquatics Center hours and programming information will be provided soon.
FREE Grand Reopening Pool Party - Olympics Style!
Dive into a day of aquatic excitement and splashes of fun at the newly renovated Coronado Aquatics Center on Saturday, August 17 from 10 am to 2 pm.
-
FREE Pool Reopening Party: Saturday, August 17, 10 am to 2 pm
- All ages are welcome. Food and drinks are included.
- Space is limited. Please pre-register for general entry.
- Register at Coronado.Ca.Us/PoolParty or call 619-522-7342 for additional information.
Share Project Update July 26 2024 on Facebook
Share Project Update July 26 2024 on Linkedin
Email Project Update July 26 2024 link
A major step in the Aquatics Center renovation has been completed. Both pools have been plastered and filled. The project is now in the middle of a two-week process to condition the pool water. Installation of a new bulkhead, which divides the pools into different areas for activities, was installed on July 26.
The final steps include waiting for the dust from the new plaster to clear prior to starting up the pools’ heaters, re-installation of the stainless-steel wire grid above the pool which acts as a bird deterrent, and the training of the Aquatics Center staff. The Project Team is on track to reopening the Center in late summer.
Photo: Installing the new bulkhead
Share Boat Launch Closed July 26 Due to Pool Construction on Facebook
Share Boat Launch Closed July 26 Due to Pool Construction on Linkedin
Email Boat Launch Closed July 26 Due to Pool Construction link
The Boat Launch parking lot, located between the Community Center and Glorietta Park will be closed on Friday, July 26 from 7 am to noon for pool construction activity. Construction crews will be using a crane to set the new bulkhead. Residents and visitors are asked to avoid the area for their safety. The pool construction is on track with the anticipated scheduled opening in mid-August.
Share Project Update 7/19/2024 on Facebook
Share Project Update 7/19/2024 on Linkedin
Email Project Update 7/19/2024 link
The Boat Launch parking lot will be closed on Wednesday, July 24 from 7 am to 12 pm for pool construction activity. During this time, construction crews will be using a crane to set the new bulkhead.
Share Project Update July 15, 2024 on Facebook
Share Project Update July 15, 2024 on Linkedin
Email Project Update July 15, 2024 link
The construction team has made great progress on the Aquatics Center Pool project. The pools’ tile installation has been finished and the plaster installation started on July 12 and was completed on July 13. Once the plaster installation has been completed, crews will immediately start filling both of the pools. The project is nearing the end of construction; however, there are still a number of steps that need to occur prior to reopening the pool.
The Project Team anticipates another five to six weeks of work to:
- allow for the pool conditioning
- clearing of the plaster dust prior to restarting the pools’ heaters
- and time to train the Aquatics staff.
The Aquatics Project team will continue to keep the community updated on the progress and the reopening schedule in the weeks ahead.
Share Project Update June 12, 2024 on Facebook
Share Project Update June 12, 2024 on Linkedin
Email Project Update June 12, 2024 link
UPDATE: June 26, 2024: The pool plaster application has been rescheduled to July 12 and 13.
June 12, 2024: Construction is more than halfway through the Aquatics Center Pool Improvement Project. The crews have completed the concrete deck placement around the pool and extensive tile installation is still ongoing. This week the pool gutters and surge tanks are being prepped for waterproofing. Crews will also be installing the new pool lights and the Recreation Pool’s refinished water feature.
Pool plaster application is currently scheduled for June 28 and 29. During these dates, the boat launch parking lot will have limited access and reduced parking. While the pool is closed for construction, the City’s Facilities staff are taking advantage of this opportunity to perform a series of maintenance projects. Currently, they are refinishing the wood supports on the west side shade structure.
Tile installation on the Aquatics Center Pools
Refinishing the wood supports on the west side shade structure.
Completed concrete deck placement around the pool
Share Project Update May 13, 2024 on Facebook
Share Project Update May 13, 2024 on Linkedin
Email Project Update May 13, 2024 link
Construction at the Aquatics Center continues to progress. The pools’ extensive tile work is ongoing. The new deck’s concrete reinforcing steel has been installed and concrete placement is underway. The project’s contractor is anticipating a total of seven days for concrete work. Two days of concrete work will occur Wednesday (May 15) and Friday (May 17). Additional concrete work is tentatively scheduled for May 21, 23, 28, 30, and June 6. During concrete construction residents should expect delays and detours around the project site. Additionally, there will be limited access and parking at the boat launch parking lot. Please note: the contractor has been permitted to start work at 5:00 am rather than 7:00 am on concrete days. The majority of the construction noise will be caused by the concrete trucks backing into place.
Share Project Update May 1, 2024 on Facebook
Share Project Update May 1, 2024 on Linkedin
Email Project Update May 1, 2024 link
The project continues to move forward through the construction process.
- 12 inches of engineered fill has been imported onto the project site and compacted. The infill will provide a cohesive and stable subsurface to support the new concrete deck.
- The pool’s deck drainage system has been installed and the project’s first concrete placement was performed to lock the drainage system into place.
- The Project Contractor anticipates seven more days of concrete placement. While the contractor is placing concrete, residents should expect limited access to the boat launch parking lot, increased vehicular traffic, and delays around the project site.
- Tentatively, concrete pour days are planned for the weeks of May 13, 20, and 27. Further updates will be provided once the schedule for the concrete days has been finalized. Please note: the contractor has been permitted to start work at 5:00 am rather than 7:00 am on concrete days. The majority of the construction noise will be caused by the concrete trucks backing into place.
- The tile installation in and around the pools is ongoing.
Concrete Slot Drain
Concrete Placement
Slot Drain
Tile Installation
Share Progress Update April 3, 2024 on Facebook
Share Progress Update April 3, 2024 on Linkedin
Email Progress Update April 3, 2024 link
The project is in its eighth week of construction and work is progressing.
- Recreations Pool's waterline tiles are being installed;
- Competition Pool’s Lane line tile mortar beds are being installed;
- New in-pool lighting conduits have been installed;
- Soil remediation continues in preparation for the new concrete deck.
Waterline Tile Installation
New Lighting Conduit
Lane Line Tile Mortar Beds
Soil Remediation Equipment
Share Progress Update March 11, 2024 on Facebook
Share Progress Update March 11, 2024 on Linkedin
Email Progress Update March 11, 2024 link
The City contractor, California Waters, continues to make progress on the demolition at the Aquatics Center. The contractor has demolished and removed the Recreation and the Competition pools’ plaster, tile, and gutter grates, and the concrete pool deck. The Competition Pool’s stainless-steel bulkhead has been removed and recycled.
During the week of March 11, the existing bird wire, which serves to deter seagulls, will be removed to accommodate construction activity. Repairs will be made to the pools’ concrete shells, and soil remediation will begin. Soil remediation is a necessary step to ensure proper placement of the new concrete deck.