Aquatics Center & Pool Improvements

Share Aquatics Center & Pool Improvements on Facebook Share Aquatics Center & Pool Improvements on Twitter Share Aquatics Center & Pool Improvements on Linkedin Email Aquatics Center & Pool Improvements link


At a glance

Constructed in 2006, the Coronado Aquatics Center and Pool were in need of immediate repair. On January 16, 2024, the City Council authorized a contract with California Waters for the Aquatics Center & Pool Improvements Project. During the construction project, the Aquatics Center and Pool has been closed. The City understands the substantial impact to the community during the closure and appreciates the community's patience while the project is completed. Once the construction is completed, the City will reopen the Coronado Aquatics Center and Pool.

Questions or concerns? Please contact us at AquaticsCenterProject@coronado.ca.us.

The project will address the following conditions and challenges:

  • 18-year-old plaster in both pools which greatly exceeded the 10-year life expectancy.
  • Competition Pool’s bulkhead has been in disrepair, creating challenges for maintenance of algae growth underneath.
  • Algae spores in the plaster cannot be eradicated until removal of the existing plaster.
  • Grates, grate ledges and tiles that need of replacement.
  • Exposed aggregate on the pool deck.
  • Recreation Pool pump to be inspected internally to ensure the pump will not fail, and the inspection cannot be completed until the pool water is drained.
  • Leaking Recreation Pool filter cannot be repaired until the pool water is drained.
  • Replacement of a failing pool heater in the Recreation Pool.

>> For construction updates, check the News Feed at the bottom of this webpage.


Construction schedule

AQUATICS CENTER & POOL CLOSURE

  • The Aquatics Center and Pool closed February 9, 2024, for the construction improvements and the anticipated reopening is August 21, 2024.
  • Construction Work: Monday – Saturday. Typical hours will be 7:00 am to 3:30 pm.


PASSHOLDER UPDATES

  • Effective January 31, 2024, all aquatics passes were temporarily suspended and will resume when the facility reopens. Sales and renewals of all aquatic's passes were also suspended. Annual Aquatics Center memberships with access to the Fitness Center have continued during the construction at no additional charge.


PROGRAMMING UPDATES


Swimming options to accommodate aquatic needs

Current pool passes are paused until the reopening of the Aquatics Center.


Scope of work

The project scope was defined by the Public Services & Engineering, Recreation & Golf Services, and Aquatic Design Group. It includes replacement to the pools’ 18-year-old plaster, repairs to the pools’ floors and walls, replacement to the pools’ tile and grout, replacement of all gutter grating, repair of damaged concrete gutters, replacement of pool deck and associated drainage, additional deck drainage to reduce standing water, water proofing of gutters and surge tanks, refinishing of existing grabrails and handrails, turf replacement, replacement of Competition Pool bulkhead, and refinishing the existing Recreation Pool water feature.


Why the Project Did Not Coincide with the 2023 Summer Competition Pool Closure

  • The Aquatics Center & Pool Improvements Capital Improvements Project was in the design phase when the Competition Pool pump failed last summer. There are many steps that must occur prior to starting construction on a CIP. Some of the steps required for the Aquatics Center & Pool Improvements Project included defining the project scope, awarding design contracts to architects/engineers, geotechnical field investigation and analysis, preparation of construction documents, and applying for permits with the required full architectural designs. Pool projects require County of San Diego Health Department and the City of Coronado review of designs and permitting, bid solicitation, and City Council authorization to award a construction contract.

  • The Competition Pool pump failure was unexpected and without notice. The progress on the CIP project continued but could not be accelerated to a pace which would have allowed for the unplanned closure during the summer of 2023 to coincide with construction of the Aquatics Center & Pool Improvements Project.

Photo: pool bulkhead before constructionPhoto: pool plaster before construction

Photo: pool tile before construction


Project Funding

The project’s construction cost is $4.5 million, which includes construction administration support, inspections, materials testing, contingency, and design services. This project is included in the FY2022-23 Capital Improvement Program.


At a glance

Constructed in 2006, the Coronado Aquatics Center and Pool were in need of immediate repair. On January 16, 2024, the City Council authorized a contract with California Waters for the Aquatics Center & Pool Improvements Project. During the construction project, the Aquatics Center and Pool has been closed. The City understands the substantial impact to the community during the closure and appreciates the community's patience while the project is completed. Once the construction is completed, the City will reopen the Coronado Aquatics Center and Pool.

Questions or concerns? Please contact us at AquaticsCenterProject@coronado.ca.us.

The project will address the following conditions and challenges:

  • 18-year-old plaster in both pools which greatly exceeded the 10-year life expectancy.
  • Competition Pool’s bulkhead has been in disrepair, creating challenges for maintenance of algae growth underneath.
  • Algae spores in the plaster cannot be eradicated until removal of the existing plaster.
  • Grates, grate ledges and tiles that need of replacement.
  • Exposed aggregate on the pool deck.
  • Recreation Pool pump to be inspected internally to ensure the pump will not fail, and the inspection cannot be completed until the pool water is drained.
  • Leaking Recreation Pool filter cannot be repaired until the pool water is drained.
  • Replacement of a failing pool heater in the Recreation Pool.

>> For construction updates, check the News Feed at the bottom of this webpage.


Construction schedule

AQUATICS CENTER & POOL CLOSURE

  • The Aquatics Center and Pool closed February 9, 2024, for the construction improvements and the anticipated reopening is August 21, 2024.
  • Construction Work: Monday – Saturday. Typical hours will be 7:00 am to 3:30 pm.


PASSHOLDER UPDATES

  • Effective January 31, 2024, all aquatics passes were temporarily suspended and will resume when the facility reopens. Sales and renewals of all aquatic's passes were also suspended. Annual Aquatics Center memberships with access to the Fitness Center have continued during the construction at no additional charge.


PROGRAMMING UPDATES


Swimming options to accommodate aquatic needs

Current pool passes are paused until the reopening of the Aquatics Center.


Scope of work

The project scope was defined by the Public Services & Engineering, Recreation & Golf Services, and Aquatic Design Group. It includes replacement to the pools’ 18-year-old plaster, repairs to the pools’ floors and walls, replacement to the pools’ tile and grout, replacement of all gutter grating, repair of damaged concrete gutters, replacement of pool deck and associated drainage, additional deck drainage to reduce standing water, water proofing of gutters and surge tanks, refinishing of existing grabrails and handrails, turf replacement, replacement of Competition Pool bulkhead, and refinishing the existing Recreation Pool water feature.


Why the Project Did Not Coincide with the 2023 Summer Competition Pool Closure

  • The Aquatics Center & Pool Improvements Capital Improvements Project was in the design phase when the Competition Pool pump failed last summer. There are many steps that must occur prior to starting construction on a CIP. Some of the steps required for the Aquatics Center & Pool Improvements Project included defining the project scope, awarding design contracts to architects/engineers, geotechnical field investigation and analysis, preparation of construction documents, and applying for permits with the required full architectural designs. Pool projects require County of San Diego Health Department and the City of Coronado review of designs and permitting, bid solicitation, and City Council authorization to award a construction contract.

  • The Competition Pool pump failure was unexpected and without notice. The progress on the CIP project continued but could not be accelerated to a pace which would have allowed for the unplanned closure during the summer of 2023 to coincide with construction of the Aquatics Center & Pool Improvements Project.

Photo: pool bulkhead before constructionPhoto: pool plaster before construction

Photo: pool tile before construction


Project Funding

The project’s construction cost is $4.5 million, which includes construction administration support, inspections, materials testing, contingency, and design services. This project is included in the FY2022-23 Capital Improvement Program.

  • Project Update July 26 2024

    Share Project Update July 26 2024 on Facebook Share Project Update July 26 2024 on Twitter Share Project Update July 26 2024 on Linkedin Email Project Update July 26 2024 link

    A major step in the Aquatics Center renovation has been completed. Both pools have been plastered and filled. The project is now in the middle of a two-week process to condition the pool water. Installation of a new bulkhead, which divides the pools into different areas for activities, was installed on July 26.

    The final steps include waiting for the dust from the new plaster to clear prior to starting up the pools’ heaters, re-installation of the stainless-steel wire grid above the pool which acts as a bird deterrent, and the training of the Aquatics Center staff. The Project Team is on track to reopening the Center in late summer.


    Photo: Installing the new bulkhead


  • Boat Launch Closed July 26 Due to Pool Construction

    Share Boat Launch Closed July 26 Due to Pool Construction on Facebook Share Boat Launch Closed July 26 Due to Pool Construction on Twitter Share Boat Launch Closed July 26 Due to Pool Construction on Linkedin Email Boat Launch Closed July 26 Due to Pool Construction link

    The Boat Launch parking lot, located between the Community Center and Glorietta Park will be closed on Friday, July 26 from 7 am to noon for pool construction activity. Construction crews will be using a crane to set the new bulkhead. Residents and visitors are asked to avoid the area for their safety. The pool construction is on track with the anticipated scheduled opening in mid-August.

  • Project Update 7/19/2024

    Share Project Update 7/19/2024 on Facebook Share Project Update 7/19/2024 on Twitter Share Project Update 7/19/2024 on Linkedin Email Project Update 7/19/2024 link

    The Boat Launch parking lot will be closed on Wednesday, July 24 from 7 am to 12 pm for pool construction activity. During this time, construction crews will be using a crane to set the new bulkhead.

  • Project Update July 15, 2024

    Share Project Update July 15, 2024 on Facebook Share Project Update July 15, 2024 on Twitter Share Project Update July 15, 2024 on Linkedin Email Project Update July 15, 2024 link

    The construction team has made great progress on the Aquatics Center Pool project. The pools’ tile installation has been finished and the plaster installation started on July 12 and was completed on July 13. Once the plaster installation has been completed, crews will immediately start filling both of the pools. The project is nearing the end of construction; however, there are still a number of steps that need to occur prior to reopening the pool.

    The Project Team anticipates another five to six weeks of work to:

    • allow for the pool conditioning
    • clearing of the plaster dust prior to restarting the pools’ heaters
    • and time to train the Aquatics staff.


    The Aquatics Project team will continue to keep the community updated on the progress and the reopening schedule in the weeks ahead.





  • Project Update June 12, 2024

    Share Project Update June 12, 2024 on Facebook Share Project Update June 12, 2024 on Twitter Share Project Update June 12, 2024 on Linkedin Email Project Update June 12, 2024 link

    UPDATE: June 26, 2024: The pool plaster application has been rescheduled to July 12 and 13.


    June 12, 2024: Construction is more than halfway through the Aquatics Center Pool Improvement Project. The crews have completed the concrete deck placement around the pool and extensive tile installation is still ongoing. This week the pool gutters and surge tanks are being prepped for waterproofing. Crews will also be installing the new pool lights and the Recreation Pool’s refinished water feature.

    Pool plaster application is currently scheduled for June 28 and 29. During these dates, the boat launch parking lot will have limited access and reduced parking. While the pool is closed for construction, the City’s Facilities staff are taking advantage of this opportunity to perform a series of maintenance projects. Currently, they are refinishing the wood supports on the west side shade structure.

    Tile installation on the Aquatics Center Pools


    Refinishing the wood supports on the west side shade structure.



    Completed concrete deck placement around the pool



  • Project Update May 13, 2024

    Share Project Update May 13, 2024 on Facebook Share Project Update May 13, 2024 on Twitter Share Project Update May 13, 2024 on Linkedin Email Project Update May 13, 2024 link

    Construction at the Aquatics Center continues to progress. The pools’ extensive tile work is ongoing. The new deck’s concrete reinforcing steel has been installed and concrete placement is underway. The project’s contractor is anticipating a total of seven days for concrete work. Two days of concrete work will occur Wednesday (May 15) and Friday (May 17). Additional concrete work is tentatively scheduled for May 21, 23, 28, 30, and June 6. During concrete construction residents should expect delays and detours around the project site. Additionally, there will be limited access and parking at the boat launch parking lot. Please note: the contractor has been permitted to start work at 5:00 am rather than 7:00 am on concrete days. The majority of the construction noise will be caused by the concrete trucks backing into place.


  • Project Update May 1, 2024

    Share Project Update May 1, 2024 on Facebook Share Project Update May 1, 2024 on Twitter Share Project Update May 1, 2024 on Linkedin Email Project Update May 1, 2024 link

    The project continues to move forward through the construction process.

    • 12 inches of engineered fill has been imported onto the project site and compacted. The infill will provide a cohesive and stable subsurface to support the new concrete deck.
    • The pool’s deck drainage system has been installed and the project’s first concrete placement was performed to lock the drainage system into place.
    • The Project Contractor anticipates seven more days of concrete placement. While the contractor is placing concrete, residents should expect limited access to the boat launch parking lot, increased vehicular traffic, and delays around the project site.
    • Tentatively, concrete pour days are planned for the weeks of May 13, 20, and 27. Further updates will be provided once the schedule for the concrete days has been finalized. Please note: the contractor has been permitted to start work at 5:00 am rather than 7:00 am on concrete days. The majority of the construction noise will be caused by the concrete trucks backing into place.
    • The tile installation in and around the pools is ongoing.


    Concrete Slot Drain


    Concrete Placement


    Slot Drain


    Tile Installation



  • Progress Update April 3, 2024

    Share Progress Update April 3, 2024 on Facebook Share Progress Update April 3, 2024 on Twitter Share Progress Update April 3, 2024 on Linkedin Email Progress Update April 3, 2024 link

    The project is in its eighth week of construction and work is progressing.

    • Recreations Pool's waterline tiles are being installed;
    • Competition Pool’s Lane line tile mortar beds are being installed;
    • New in-pool lighting conduits have been installed;
    • Soil remediation continues in preparation for the new concrete deck.

    Waterline Tile Installation


    New Lighting Conduit

    Lane Line Tile Mortar Beds


    Soil Remediation Equipment

  • Progress Update March 11, 2024

    Share Progress Update March 11, 2024 on Facebook Share Progress Update March 11, 2024 on Twitter Share Progress Update March 11, 2024 on Linkedin Email Progress Update March 11, 2024 link

    The City contractor, California Waters, continues to make progress on the demolition at the Aquatics Center. The contractor has demolished and removed the Recreation and the Competition pools’ plaster, tile, and gutter grates, and the concrete pool deck. The Competition Pool’s stainless-steel bulkhead has been removed and recycled.

    During the week of March 11, the existing bird wire, which serves to deter seagulls, will be removed to accommodate construction activity. Repairs will be made to the pools’ concrete shells, and soil remediation will begin. Soil remediation is a necessary step to ensure proper placement of the new concrete deck.


  • Crew Busy Demolishing Recreation Pool & Deck

    Share Crew Busy Demolishing Recreation Pool & Deck on Facebook Share Crew Busy Demolishing Recreation Pool & Deck on Twitter Share Crew Busy Demolishing Recreation Pool & Deck on Linkedin Email Crew Busy Demolishing Recreation Pool & Deck link

    Last week, construction started on the Aquatics Center and Pool rehabilitation project. Built in 2006, the Center is in need of a complete overhaul. Currently, the City contractors are busy demolishing the recreation pool and deck. With these construction activities, the parking at the Community Center is limited. As soon as the demolition phase is completed, additional parking spaces will become available.

    The Aquatics Project Team appreciates the community's patience while the improvements are underway.




Page last updated: 26 Jul 2024, 01:29 PM