Project Update April 25, 2023

The City contractor began work April 17 on Phase 1 at Cays Park Court 5 and the basketball court. During the footing excavation, the contractor found that the tennis court is made of post tensioned concrete. What this means is that in order to install the footings properly, the existing post tensioned cables within the concrete slab must be avoided. This caused a few days of delay to rework the footing sizes and locations.

Work completed to date:

  • Pickleball net posts have been installed.
  • Pickleball barrier fence posts have been dug. Concrete footings will be poured after a City inspection.
  • Basketball court joints, primer, and green color coat have been completed.

Upcoming activities this week:

  • Installation of pickleball fence and gates.
  • Resurfacing and striping of pickleball court 5.
  • Paint final blue color coat at free throw lane and circles on basketball court, followed by white striping.

Opening dates will be provided once the surfaces have cured.

Phase 1: Court 5 and the basketball court

Phase 2: Courts 1 through 4

Anticipated time at Cays Park: The Cays Park phase is expected to be finished by May 19 (2023). Once Cays Park is completed, the contractor will move to the Coronado Public Library tennis courts, and then to the Tennis Center Complex.

Contact: Impact Activities for scheduling/court availability during the phased closure at 619.522.2650 or online at Impactactivities.com/Coronado.