Court Resurfacing & Improvements Project

Share on Facebook Share on Twitter Share on Linkedin Email this link

AT A GLANCE

The Court Resurfacing and Improvements Project will increase the quality of play and create a positive impact for residents enjoying the community’s outdoor tennis and pickleball courts. The construction includes resurfacing and restriping of tennis and pickleball courts at City facilities.

The project began well ahead of the construction start in April 2023 with months of engagement, a community survey, and meetings with the Coronado Tennis Association and Pickleball Coronado Association to understand the community's needs. The first phase began at Cays Park. To create more playing areas for the growing number of pickleball users, crews converted two existing tennis courts in Cays Park into dedicated pickleball courts. The first pickleball courts in the City of Coronado. Construction crews will begin the next phase on June 5 at the Tennis Center, then finish up at the Coronado Library tennis courts.

PROJECT UPDATES

Check the News Feed below for project updates.

TIMELINE

Construction Phase 1: April 2023 to June 5, 2023 (Cays Park Pickleball Courts A-D opened May 15, Courts E-H open May 27, and Courts 1-3 to open June 1.
Construction Phase 2: June 5, 2023, to Summer 2023 beginning at the Tennis Center.
Construction Work Hours: 7am to 7pm (No night, weekend or holiday work)

HISTORY
The Court Resurfacing & Improvements Project construction was approved by the City Council in July 2022 when the City Council agreed to add pickleball courts in Coronado. On November 15, 2022, the City Council approved the lowest bid contractor, TrueLine Construction and Surfacing, Inc. to build the project. The City of Coronado operates and maintains 15 USTA standard doubles sized tennis courts. The current configuration provides 14 tennis courts, 8 temporary pickleball courts, 1 basketball court, and 1 practice court.

BUDGET
The $465,220 project is being funded from the City’s Capital Projects Budget and the Recreation Tennis Maintenance Budget.

AT A GLANCE

The Court Resurfacing and Improvements Project will increase the quality of play and create a positive impact for residents enjoying the community’s outdoor tennis and pickleball courts. The construction includes resurfacing and restriping of tennis and pickleball courts at City facilities.

The project began well ahead of the construction start in April 2023 with months of engagement, a community survey, and meetings with the Coronado Tennis Association and Pickleball Coronado Association to understand the community's needs. The first phase began at Cays Park. To create more playing areas for the growing number of pickleball users, crews converted two existing tennis courts in Cays Park into dedicated pickleball courts. The first pickleball courts in the City of Coronado. Construction crews will begin the next phase on June 5 at the Tennis Center, then finish up at the Coronado Library tennis courts.

PROJECT UPDATES

Check the News Feed below for project updates.

TIMELINE

Construction Phase 1: April 2023 to June 5, 2023 (Cays Park Pickleball Courts A-D opened May 15, Courts E-H open May 27, and Courts 1-3 to open June 1.
Construction Phase 2: June 5, 2023, to Summer 2023 beginning at the Tennis Center.
Construction Work Hours: 7am to 7pm (No night, weekend or holiday work)

HISTORY
The Court Resurfacing & Improvements Project construction was approved by the City Council in July 2022 when the City Council agreed to add pickleball courts in Coronado. On November 15, 2022, the City Council approved the lowest bid contractor, TrueLine Construction and Surfacing, Inc. to build the project. The City of Coronado operates and maintains 15 USTA standard doubles sized tennis courts. The current configuration provides 14 tennis courts, 8 temporary pickleball courts, 1 basketball court, and 1 practice court.

BUDGET
The $465,220 project is being funded from the City’s Capital Projects Budget and the Recreation Tennis Maintenance Budget.

  • City Officially Reopens Cays Park Tennis & Pickleball Courts

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The City officially celebrated the completion of Phase One of the Tennis and Pickleball Court Resurfacing Project at Cays Park on June 5. The City project includes the resurfacing and restriping of tennis and pickleball courts at City facilities.

    The project began well ahead of the construction start in April 2023 with months of engagement, a community survey, and meetings with the Coronado Tennis Association and Pickleball Coronado Association to understand the community's needs. The first phase began at Cays Park. To create more playing areas for the growing number of pickleball users, crews converted two existing tennis courts in Cays Park into dedicated pickleball courts, creating eight new pickleball courts. The first public pickleball courts in the city of Coronado.

    TENNIS & PICKLEBALL COURT RESURFACING PROJECT TIMELINE

    Construction Phase 1: April 2023 to June 5, 2023
    Construction Phase 2: June 5, 2023 to Summer 2023 beginning at the Tennis Center and finishing at the library tennis courts.

  • Phase One Completion Celebration, June 5

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The City of Coronado is celebrating the completion of Phase One of the Tennis and Pickleball Court Resurfacing Project. The community is invited to the reopening of the newly resurfaced and restriped tennis and pickleball Courts at Cays Park on June 5, 2023, at 2:30 pm. Cays Park is located at 99 Grand Caribe Isle. The City will officially reopen the newly resurfaced and restriped courts for both tennis and pickleball players. Refreshments provided afterwards.

    The City’s Tennis and Pickleball Court Resurfacing Project included months of engagement and community surveys and meetings to understand the attitudes and needs of tennis and pickleball and what would be appropriate before construction started in the spring. Next, construction will move to the Tennis Center and then on to the Coronado Public Library courts where work is expected to be completed in the summer, 2023.



  • Project Update May 23, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    UPDATED TIMELINE
    *Weather permitting and on-time material delivery

    Construction Phase 1: April 2023 to June 5, 2023 *(Cays Park Pickleball Courts A-D (formerly Court 5) opened May 15, Courts E-H open May 27 and Courts 1-3 open June 5.
    Construction Phase 2: June 5, 2023, to Summer 2023
    Construction Work Hours: 7am to 7pm (No night, weekend or holiday work)

  • New Cays Park Court Numbering Updated

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The tennis and pickleball courts at Cays Park have been renumbered. The new system is in place now.

  • Project Update May 15, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The City contractor began work April 17 on Phase 1 at Cays Park Court 5 and the basketball court. Footing excavation caused a few days of delay to rework the footing sizes and locations. On May 15 (2023), the basketball court and pickleball court 5 opened.

    Work completed to date:

    • Pickleball Court 5 completed. Basketball court completed.
    • Pickleball barrier fence posts have been set on Court 1.


    Upcoming activities this week:

    • Installation of pickleball fence and gates Court 1.
    • Tennis courts 2 through 4: Clean, grind, repair spots, caulk joints, and water test.

    Project Construction Timeline:

    • Phase 1 Completed: Basketball court is open. Court 5 is open (May 15).
    • Phase 2: Courts 1 through 4 target completion May 29.
    • Anticipated completion at Cays Park: The Cays Park phase is expected to be finished by May 29 (2023). Once completed, the contractor will move to the Tennis Center Complex and then the Coronado Public Library.


  • Project Update April 25, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The City contractor began work April 17 on Phase 1 at Cays Park Court 5 and the basketball court. During the footing excavation, the contractor found that the tennis court is made of post tensioned concrete. What this means is that in order to install the footings properly, the existing post tensioned cables within the concrete slab must be avoided. This caused a few days of delay to rework the footing sizes and locations.

    Work completed to date:

    • Pickleball net posts have been installed.
    • Pickleball barrier fence posts have been dug. Concrete footings will be poured after a City inspection.
    • Basketball court joints, primer, and green color coat have been completed.

    Upcoming activities this week:

    • Installation of pickleball fence and gates.
    • Resurfacing and striping of pickleball court 5.
    • Paint final blue color coat at free throw lane and circles on basketball court, followed by white striping.

    Opening dates will be provided once the surfaces have cured.

    Phase 1: Court 5 and the basketball court

    Phase 2: Courts 1 through 4

    Anticipated time at Cays Park: The Cays Park phase is expected to be finished by May 19 (2023). Once Cays Park is completed, the contractor will move to the Coronado Public Library tennis courts, and then to the Tennis Center Complex.

    Contact: Impact Activities for scheduling/court availability during the phased closure at 619.522.2650 or online at Impactactivities.com/Coronado.



  • Project Update April 5, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Contractor has been waiting for drier weather and consistently warmer temperatures to comply with the surfacing material’s installation specifications. They anticipate the weather and temperature requirements will be met by April 17, so that they can begin work at the Cays Park location on that date.

    Phase 1: Court 5 and the basketball court

    Phase 2: Courts 1 through 4.

    Anticipated time at Cays Park: 25 working days after work begins. The newly resurfaced and restriped courts are expected to be completed by May 19, 2023. Once Cays Park is completed, the Contractor will move to the Library tennis courts, and then to the Tennis Center Complex.

    Contact: Impact Activities for scheduling/court availability during the phased closure. P: 619.522. 2650 Web: Impactactivities.com/Coronado

  • Project Update March 6, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As a result of the wet, cold weather the area has been experiencing lately, the City’s Court Resurfacing and Improvements Project has been slightly delayed. This project is important because the quality of play will be improved by refreshing the surfaces and restriping the City’s courts for tennis and pickleball. Because the material used in resurfacing is sensitive to moisture and temperature, the contractor must wait to apply the court surfaces in dry and warmer temperatures. Resurfacing a court is best done when the outside temperature is 50 degrees and rising for the duration of the surface installation. If the temperatures are too wet or cold, the surface won’t cure properly, and may lead to the surface cracking and additional repairs further down the line. Waiting for the correct temperatures will go a long way toward providing the best outcome for the community's courts.

    The supplies and materials for the project have been delivered and the contractor anticipates work beginning in early April, barring weather-related issues.

Page last updated: 06 Jun 2023, 09:17 AM