Share Project Update August 2, 2023 on Facebook
Share Project Update August 2, 2023 on Linkedin
Email Project Update August 2, 2023 link
Construction Phase 2 Tennis Center: All courts open for play, including the practice courts.
Construction Phase 3: Coronado Library: The City contractor is currently working on resurfacing Courts 1 and 2 at the Library. The work is scheduled to be completed by Friday, August 4. The courts will be locked over the weekend to allow for curing of the material. Both courts will be open for play on Monday, August 7.
Share Project Update July 24, 2023 on Facebook
Share Project Update July 24, 2023 on Linkedin
Email Project Update July 24, 2023 link
During the surface preparation, it was discovered that Courts 1. 2, and 8 at the Tennis Center have several pockets beneath the surface. To minimize the probability of future cracking and bubbling, additional work to grind the courts to bare concrete was authorized. The Contractor completed patching the divets and cracks after removing the old surface materials.
The City appreciates the tennis community’s patience and understanding over the noise and dust created during this phase. The contractor is currently (week of July 24) applying the resurface layers and plans to finish them by the end of next week. Once the surfaces have cured over the weekend, assuming all goes well, those courts will be available for play on Thursday, July 27.
Share Project Update July 7, 2023 on Facebook
Share Project Update July 7, 2023 on Linkedin
Email Project Update July 7, 2023 link
July 7, 2023
During the surface preparation, it was discovered that Courts 1. 2, and 8 at the Tennis Center have several pockets beneath the surface. To minimize the probability of future cracking and bubbling, additional work to grind the courts to bare concrete has been authorized. The City contractor plans to provide an updated schedule once they can visually see the concrete surface condition to determine the degree of patching required. It is anticipated this grinding phase will run through July 14. A drain test, patching the divets and cracks and then applying the resurface layers will follow.
Courts 1,2 and 8 in progress. Junior tennis court line striping on courts 5, 6, 7 will occur once these courts are complete.
Share Courts 5, 6, & 7 Open at the Tennis Center on Facebook
Share Courts 5, 6, & 7 Open at the Tennis Center on Linkedin
Email Courts 5, 6, & 7 Open at the Tennis Center link
On Monday, June 19, courts 5, 6, and 7 at the Tennis Center opened. Courts 4, 5 and the Practice Court are in progress, followed by Phase 3, courts 1, 2 and 8.
Photo: Court 6 looking toward court 7 at the Tennis Center. June 19, 2023
Share City Officially Reopens Cays Park Tennis & Pickleball Courts on Facebook
Share City Officially Reopens Cays Park Tennis & Pickleball Courts on Linkedin
Email City Officially Reopens Cays Park Tennis & Pickleball Courts link
The City officially celebrated the completion of Phase One of the Tennis and Pickleball Court Resurfacing Project at Cays Park on June 5. The City project includes the resurfacing and restriping of tennis and pickleball courts at City facilities.
The project began well ahead of the construction start in April 2023 with months of engagement, a community survey, and meetings with the Coronado Tennis Association and Pickleball Coronado Association to understand the community's needs. The first phase began at Cays Park. To create more playing areas for the growing number of pickleball users, crews converted two existing tennis courts in Cays Park into dedicated pickleball courts, creating eight new pickleball courts. The first public pickleball courts in the city of Coronado.
TENNIS & PICKLEBALL COURT RESURFACING PROJECT TIMELINE
Construction Phase 1: April 2023 to June 5, 2023
Construction Phase 2: June 5, 2023 to Summer 2023 beginning at the Tennis Center and finishing at the library tennis courts.
Share Phase One Completion Celebration, June 5 on Facebook
Share Phase One Completion Celebration, June 5 on Linkedin
Email Phase One Completion Celebration, June 5 link
The City of Coronado is celebrating the completion of Phase One of the Tennis and Pickleball Court Resurfacing Project. The community is invited to the reopening of the newly resurfaced and restriped tennis and pickleball Courts at Cays Park on June 5, 2023, at 2:30 pm. Cays Park is located at 99 Grand Caribe Isle. The City will officially reopen the newly resurfaced and restriped courts for both tennis and pickleball players. Refreshments provided afterwards.
The City’s Tennis and Pickleball Court Resurfacing Project included months of engagement and community surveys and meetings to understand the attitudes and needs of tennis and pickleball and what would be appropriate before construction started in the spring. Next, construction will move to the Tennis Center and then on to the Coronado Public Library courts where work is expected to be completed in the summer, 2023.
Share Project Update May 23, 2023 on Facebook
Share Project Update May 23, 2023 on Linkedin
Email Project Update May 23, 2023 link
UPDATED TIMELINE
*Weather permitting and on-time material delivery
Construction Phase 1: April 2023 to June 5, 2023 *(Cays Park Pickleball Courts A-D (formerly Court 5) opened May 15, Courts E-H open May 27 and Courts 1-3 open June 5.
Construction Phase 2: June 5, 2023, to Summer 2023
Construction Work Hours: 7am to 7pm (No night, weekend or holiday work)
Share New Cays Park Court Numbering Updated on Facebook
Share New Cays Park Court Numbering Updated on Linkedin
Email New Cays Park Court Numbering Updated link
The tennis and pickleball courts at Cays Park have been renumbered. The new system is in place now.
Share Project Update May 15, 2023 on Facebook
Share Project Update May 15, 2023 on Linkedin
Email Project Update May 15, 2023 link
The City contractor began work April 17 on Phase 1 at Cays Park Court 5 and the basketball court. Footing excavation caused a few days of delay to rework the footing sizes and locations. On May 15 (2023), the basketball court and pickleball court 5 opened.
Work completed to date:
- Pickleball Court 5 completed. Basketball court completed.
- Pickleball barrier fence posts have been set on Court 1.
Upcoming activities this week:
- Installation of pickleball fence and gates Court 1.
- Tennis courts 2 through 4: Clean, grind, repair spots, caulk joints, and water test.
Project Construction Timeline:
-
Phase 1 Completed: Basketball court is open. Court 5 is open (May 15).
-
Phase 2: Courts 1 through 4 target completion May 29.
-
Anticipated completion at Cays Park: The Cays Park phase is expected to be finished by May 29 (2023). Once completed, the contractor will move to the Tennis Center Complex and then the Coronado Public Library.
Share Project Update April 25, 2023 on Facebook
Share Project Update April 25, 2023 on Linkedin
Email Project Update April 25, 2023 link
The City contractor began work April 17 on Phase 1 at Cays Park Court 5 and the basketball court. During the footing excavation, the contractor found that the tennis court is made of post tensioned concrete. What this means is that in order to install the footings properly, the existing post tensioned cables within the concrete slab must be avoided. This caused a few days of delay to rework the footing sizes and locations.
Work completed to date:
- Pickleball net posts have been installed.
- Pickleball barrier fence posts have been dug. Concrete footings will be poured after a City inspection.
- Basketball court joints, primer, and green color coat have been completed.
Upcoming activities this week:
- Installation of pickleball fence and gates.
- Resurfacing and striping of pickleball court 5.
- Paint final blue color coat at free throw lane and circles on basketball court, followed by white striping.
Opening dates will be provided once the surfaces have cured.
Phase 1: Court 5 and the basketball court
Phase 2: Courts 1 through 4
Anticipated time at Cays Park: The Cays Park phase is expected to be finished by May 19 (2023). Once Cays Park is completed, the contractor will move to the Coronado Public Library tennis courts, and then to the Tennis Center Complex.
Contact: Impact Activities for scheduling/court availability during the phased closure at 619.522.2650 or online at Impactactivities.com/Coronado.