Project Update July 7, 2023
July 7, 2023
During the surface preparation, it was discovered that Courts 1. 2, and 8 at the Tennis Center have several pockets beneath the surface. To minimize the probability of future cracking and bubbling, additional work to grind the courts to bare concrete has been authorized. The City contractor plans to provide an updated schedule once they can visually see the concrete surface condition to determine the degree of patching required. It is anticipated this grinding phase will run through July 14. A drain test, patching the divets and cracks and then applying the resurface layers will follow.
Courts 1,2 and 8 in progress. Junior tennis court line striping on courts 5, 6, 7 will occur once these courts are complete.
Consultation has concluded