Project Update April 5, 2023

The Contractor has been waiting for drier weather and consistently warmer temperatures to comply with the surfacing material’s installation specifications. They anticipate the weather and temperature requirements will be met by April 17, so that they can begin work at the Cays Park location on that date.

Phase 1: Court 5 and the basketball court

Phase 2: Courts 1 through 4.

Anticipated time at Cays Park: 25 working days after work begins. The newly resurfaced and restriped courts are expected to be completed by May 19, 2023. Once Cays Park is completed, the Contractor will move to the Library tennis courts, and then to the Tennis Center Complex.

Contact: Impact Activities for scheduling/court availability during the phased closure. P: 619.522. 2650 Web: Impactactivities.com/Coronado