Project Update May 8, 2026
Start up and testing activities at the new pump station are ongoing. The new sewer pump station has completed the testing requirements for the demonstration phase along with 4 of the new storm water pumps. The contractor is modifying the temporary recirculation piping to continue with testing for the 3 remaining storm water pumps. Once the demonstration testing has been completed successfully, the new station will perform a 10-day operational test to ensure the system is working properly; once this phase is completed the City will take operational control over the new station. The 10-day test is anticipated to begin at the end of this month. 