Share Project Update: August 9, 2024 on Facebook
Share Project Update: August 9, 2024 on Linkedin
Email Project Update: August 9, 2024 link
Construction continues on the Parker Pump Station project. Large excavation is taking place, and a new 48-inch storm drainpipe is being installed on the new trash rack structure. Crews have excavated the area to the west of the new storm drain wet well, in order to construct a valve vault structure. Utility installation has also started along Coronado Avenue. This work involves constructing new sewer and storm drainpipe and manholes.
The intersection closure at Coronado Avenue and Eighth Street remains in effect with an anticipated reopening in spring, 2025. This will allow the street work to be completed and will keep pedestrians and vehicles safe around the work zone.
Share Project Update: May 31, 2024 on Facebook
Share Project Update: May 31, 2024 on Linkedin
Email Project Update: May 31, 2024 link
The construction on the new Parker Pump Station at Eighth Street and Coronado Avenue is progressing. Recently, the walls for the new storm water trash rack structure were poured and the City contractor is installing the interior walls and the pump pedestals inside the storm water wet well.
Ongoing work is progressing on the waterproofing of the new pump station structures and backfilling the large excavation. Once completed, the Parker Pump Station will improve operational efficiency and prevent flooding in homes and stormwater.
Share Project Update April 16, 2024 on Facebook
Share Project Update April 16, 2024 on Linkedin
Email Project Update April 16, 2024 link
The new storm water wet well walls were poured on March 18, marking a significant milestone in the project. A total of 41 concrete trucks were onsite throughout the day with a total of 400 cubic yards of concrete placed. Since then, the contractor has been focused on curing the new walls, waterproofing the structure and partially backfilling the deep excavation.
In the next few weeks, the contractor will be forming and pouring the interior walls of the storm water wet well structure and constructing the new influent storm water trash structure, designed to capture any debris prior to entering the wet well structure.
Share Project Status March 5, 2024 on Facebook
Share Project Status March 5, 2024 on Linkedin
Email Project Status March 5, 2024 link
The temporary storm bypass system put in place due to the January 22 storm event has been removed because the existing storm water pumps have been repaired. Construction operations resumed at the end of February. The City contractor Filanc has started placing the outside wall formwork for the new storm water wet well structure. The formwork or surface of the form and framing used to contain and shape wet concrete until it is self-supporting is now being placed and is expected to be completed within the next two weeks.
Share Project Status February 14, 2024 on Facebook
Share Project Status February 14, 2024 on Linkedin
Email Project Status February 14, 2024 link
Progress on construction of the new Parker Pump Station was significantly impacted by the rain event that took place on January 22, 2024. Since that time, Filanc has been assisting the City in recovery efforts and has implemented a complete bypass of the storm water system, while the City works to repair the existing storm water pumps which were damaged during the storm.
The bypass system was designed and installed within a week to prepare for the subsequent storm – a remarkable accomplishment given the layout of the site and the pump capacity needed (36,000 gallons per minute). Work on storm water pump repairs is currently on track to be completed in early March 2024 (or sooner) and will allow Filanc to return to “normal” construction operations.
Share Project Status January 3, 2024 on Facebook
Share Project Status January 3, 2024 on Linkedin
Email Project Status January 3, 2024 link
Construction of the project is progressing inside the large excavation; the inside wall forms have been set for the new storm water wet well and now the reinforcement is being placed. The concrete pour for the walls is anticipated to take place in late January which will mark a significant project milestone.
The project schedule has been updated and due to unanticipated procurement lead times for certain items, the revised project completion date has been extended to Spring 2025. The City and Filanc have collaborated in an effort to reduce the impacts to the schedule with looking at alternative suppliers, cost incentives, etc.; but labor shortages, along with a significant increase in demand for products have been experienced industry-wide which have resulted in lead times as long as 60 weeks for fabrication of some components. The City will continue to explore other avenues to expedite the materials in hopes to improve the completion date.
In addition, the intersection closure will extend to Summer 2024. This extension is necessary to accommodate the revised project schedule and associated construction operation sequencing.
The City appreciates the community's continued patience during construction.
Share Project Status November 27, 2023 on Facebook
Share Project Status November 27, 2023 on Linkedin
Email Project Status November 27, 2023 link
The City contractor has poured the floor slab of the new storm water wet well and partially backfilled the large excavation to the top of the floor slab. Preparations are now taking place to install the wall forms of the structure with an anticipated concrete pour date in January.
Share Project Status October 31, 2023 on Facebook
Share Project Status October 31, 2023 on Linkedin
Email Project Status October 31, 2023 link
The contractor has completed the waterproofing on the exterior of the walls for the flowmeter vault and has formed the deck of the structure. Work continues to progress on installing new sections of 24-inch and 54-inch pipelines at the rear of the site. Work continued in the large excavation with placement of 3 feet of crushed rock and geotextile fabric; a waste slab was poured, and the bottom of the waterproofing material has been installed. In the coming weeks, the contractor will be placing the reinforcement for the floor slab.
Share Project Status October 6, 2023 on Facebook
Share Project Status October 6, 2023 on Linkedin
Email Project Status October 6, 2023 link
The City contractor is continuing work on the flowmeter vault, which is in the rear of the site with the concrete pour, for the walls that were finished last week. Crews are working to strip the formwork to allow for the installation of the waterproofing material prior to backfilling. The progress for the large excavation has slowed with additional shoring work; an additional 3-4 foot of excavation is needed for the contractor to move on to placing the materials for the foundation for the storm drain wet well structure.
Share Project Status June 28, 2023 on Facebook
Share Project Status June 28, 2023 on Linkedin
Email Project Status June 28, 2023 link
The construction on the new Parker Pump Station, located at Eighth Street and Coronado Avenue is progressing. This critical infrastructure is responsible for collecting stormwater and sanitary sewer flows.
The City contractor continues to work on the excavation, where the storm drain wet well will be constructed. The third and final set of supports for the shoring is currently being installed. This will allow the crews the ability to excavate to the final elevation.