Project Status March 5, 2024
The temporary storm bypass system put in place due to the January 22 storm event has been removed because the existing storm water pumps have been repaired. Construction operations resumed at the end of February. The City contractor Filanc has started placing the outside wall formwork for the new storm water wet well structure. The formwork or surface of the form and framing used to contain and shape wet concrete until it is self-supporting is now being placed and is expected to be completed within the next two weeks.