Project Update December 13, 2024
The contractor, Filanc continues to move forward with construction and has begun work associated with bringing in power to the new pump station; these activities include pouring a concrete pad for the new switchgear, installation of new conduits, SDG&E trench inspections, third party testing of the new equipment, and coordinating with SDG&E for the installation of a new transformer. Work also continues on the installation of the new 48-inch storm drainpipe, modifications to an existing storm drain cleanout, and laying the storm water discharge piping.