Project Update December 13, 2024

The contractor, Filanc continues to move forward with construction and has begun work associated with bringing in power to the new pump station; these activities include pouring a concrete pad for the new switchgear, installation of new conduits, SDG&E trench inspections, third party testing of the new equipment, and coordinating with SDG&E for the installation of a new transformer. Work also continues on the installation of the new 48-inch storm drainpipe, modifications to an existing storm drain cleanout, and laying the storm water discharge piping.



Share Project Update December 13, 2024 on Facebook Share Project Update December 13, 2024 on Twitter Share Project Update December 13, 2024 on Linkedin Email Project Update December 13, 2024 link
#<Object:0x000000002d626358>