Project Update November 21, 2025

Construction has been progressing with the new pump station. The contractor has installed most of the discharge piping, pump guide rails and associated bracing. The hydrostatic testing for the new forcemains and discharge piping has begun with the first test successful for the piping connected to the 54-inch storm water forcemain. The electrical subcontractor is continuing with the electrical and control wiring.

Share Project Update November 21, 2025 on Facebook Share Project Update November 21, 2025 on Twitter Share Project Update November 21, 2025 on Linkedin Email Project Update November 21, 2025 link
#<Object:0x00007f6e9059d3b8>