Project Update August 8, 2025

This week, the Parker Pump Station Replacement Project reached a major milestone with the installation of sewer and storm water pumps for the new stations. The upgrade includes seven storm water pumps of various sizes and two sewer pumps. Crews are now working on wiring to connect the pumps and valves to the motor control center in the new Control Building. Over the next few weeks, mechanical work will continue with the installation of discharge piping.