Project Update January 12, 2026
The discharge piping inside the storm wet well is currently being coated to ensure it is properly protected from the conditions inside the well. Crews are also working on the architectural finishes of the control building with the installation of the water barrier and furring strips in preparation for installing the cladding material. The electrical subcontractor is constructing a duct bank to route conduit and wiring from the storm water trash rack structure to the control building and is also working to installing instruments and check valve indicators. The contractor is working towards testing and startup of the new station which is anticipated to begin within the next one to two months.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends