Project Status June 13, 2023

Completed Activities

  • Shoring subcontractor mobilized and began sheet-pile installation
  • Significant progress seen on the East shoring wall after adjusting installation methods
  • Contractor utilizing a monitoring prism to record movement
  • Last set of sheets driven to the design depth on the South shoring wall
  • Excavation has reached a depth of 24 feet (bgs)below ground surface on both the South and North shoring walls to commence waler installation
  • Completed the first row of waler installation

Upcoming Activities

  • Second set of waler installation began on June 13 and will continue throughout the following week
  • Excavation to a depth of 36 feet bgs and the third set of waler installation will follow
  • Stockpile management and soil export will continue over the next few weeks
  • Bypass piping installation is scheduled to begin in the later part next week