Project Status March 6, 2023

The Construction contractor is prepping for larger scopes of work after the latest rain events. Below are the latest construction updates:

  • Effluent piping continues to be constructed from the desilting tank to the existing catch basin
  • Began drilling dewatering wells
  • Continue constructing the dewatering well discharge piping
  • The intersection at Eighth and Coronado Avenue has been closed and construction fencing is being installed.
  • Demolition of existing masonry wall and footing

Upcoming activities

  • Electrical work to power each dewatering pump
  • Dewatering for deep underground structures
  • Shoring contractor will mobilize heavy equipment to begin sheet-pile installation.