Project Update August 6, 2026

The old Parker Pump Station has been partially abandoned in place with the components of the station removed, such as the existing pumps, valves, and electronics. The upper portion of the subterranean structure has been demolished, and the contractor is now laying out the limits of the concrete pad for the permanent generator and the underground conduits. Within the next few weeks, the contractor will also be working on final force main piping modifications and onsite underground electrical for the irrigation system.