Project Update February 20, 2026
TEMPORARY POWER OUTAGE TUESDAY, FEBRUARY 24; 8AM – 11AM
Work continues towards startup and testing of the new pump station. The next critical-path step towards startup is the upsizing of an existing SDG&E electrical transformer and the upgrade/changing of fuses on two utility poles. Today, the City was notified by SDG&E that this work has been scheduled to take place on Tuesday, February 24. In order for this work to be completed SDG&E will need to temporarily turn off the power to the transformer and utility poles which will also affect homes along the west side of the 600, 700, and 800 blocks of Coronado Avenue. The work and associated power loss is scheduled to take place from 8:00am to 11:00am. SDG&E will be notifying affected homes via door-hangers. We apologize for this inconvenience.