Project update March 13, 2026
Testing of the new pump station has begun this week with the contractor performing witness loop checks for all the new field instruments to verify the wiring is correct and the system is functional. Once this is completed the pre-demonstration testing will continue with the motor control center, program logic controller, switchboard, valves and pumps.
This testing will continue through the month and once the pre-demonstration phase has passed, the contractor will continue to the demonstration phase to test the facility using a recirculation system to route the water to test each pump.