Project Update September 21, 2026
On 9/18, the concrete pad for the permanent generator was poured along with the footings for the enclosure and planters. The permanent generator is expected to be placed and anchored within the next two weeks then the construction of the masonry walls for the enclosure will begin. The temporary generators—currently providing backup power to the new pump station—have been relocated to the rear of the site to allow final grading of the site work to proceed.

Share Project Update September 21, 2026 on Facebook
Share Project Update September 21, 2026 on X (formerly Twitter)
Share Project Update September 21, 2026 on Linkedin
Email Project Update September 21, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends