Project Update September 21, 2026

On 9/18, the concrete pad for the permanent generator was poured along with the footings for the enclosure and planters. The permanent generator is expected to be placed and anchored within the next two weeks then the construction of the masonry walls for the enclosure will begin. The temporary generators—currently providing backup power to the new pump station—have been relocated to the rear of the site to allow final grading of the site work to proceed.