Parker Pump Station Replacement Project

Share Parker Pump Station Replacement Project on Facebook Share Parker Pump Station Replacement Project on X (formerly Twitter) Share Parker Pump Station Replacement Project on Linkedin Email Parker Pump Station Replacement Project link

AT A GLANCE

The City broke ground at the project site on January 6, 2023. The Parker Pump Station Replacement Project is vital to the City of Coronado's current and future infrastructure and is the largest of 20 pump stations citywide. The City is investing $32 million to replace the existing, aging Parker Pump Station with a new pump station. This critical infrastructure, located at 8th Street and Coronado Avenue, is responsible for collecting stormwater and sanitary sewer flows. The new pump station will improve operational efficiency and resiliency of the system. An additional 6,000 square feet of green space will also be added for the neighborhood to enjoy.


PROJECT UPDATES

Check the News Feed below for project updates. Sign up for e-updates under the right navigation "Get Updates."


SCHEDULE

Commissioning of the new station is anticipated to occur at the beginning of 2026. Once commissioning is completed, the old station will be partially removed with most of the underground structure to be abandoned in place. Subsequently, construction of the permanent generator enclosure, green space and other site work will take place and is anticipated to take approximately three months once commissioning is completed. Project completion is anticipated by second quarter of 2026.


PROJECT BACKGROUND

Located at Eighth Street at Coronado Avenue, the existing Parker Pump Station was constructed in 1983 and services both storm water and wastewater flows. The new Parker Pump Station will replace the current aging and failing station. The Parker Pump Station is a critical piece of infrastructure responsible for collecting storm water from 150 acres and discharging the flow to the North Beach outfall along with collecting sanitary sewer flows in the Country Club area and routing these flows to the sewer main along Alameda Boulevard.. The replacement project will completely rebuild the Parker Pump Station to provide service for generations and better protect the pump station from impacts from flooding and storm surge.


Rendering of new Parker Pump Station

PROJECT DETAILS

  • Provide a permanent generator onsite to strengthen the reliability of the station during power outages.

  • Isolate the sanitary sewer and storm water underground structures to minimize the risk of comingled flows.

  • Construct all electrical components above ground and housed in a new Controls Building the eliminate the risk of compromising the equipment to flooding should a significant rain event occur.

  • Reconfiguration of the site to provide approximately 6,000 square feet of publicly accessible green space.

  • Relocation of all planned above-ground structures to approximately 75 feet behind the face of curb along Coronado Avenue.

  • Significantly reduce the need for a temporary, above-ground storm water and wastewater bypass system during construction by keeping the existing pump station operational throughout construction of the new station.

AT A GLANCE

The City broke ground at the project site on January 6, 2023. The Parker Pump Station Replacement Project is vital to the City of Coronado's current and future infrastructure and is the largest of 20 pump stations citywide. The City is investing $32 million to replace the existing, aging Parker Pump Station with a new pump station. This critical infrastructure, located at 8th Street and Coronado Avenue, is responsible for collecting stormwater and sanitary sewer flows. The new pump station will improve operational efficiency and resiliency of the system. An additional 6,000 square feet of green space will also be added for the neighborhood to enjoy.


PROJECT UPDATES

Check the News Feed below for project updates. Sign up for e-updates under the right navigation "Get Updates."


SCHEDULE

Commissioning of the new station is anticipated to occur at the beginning of 2026. Once commissioning is completed, the old station will be partially removed with most of the underground structure to be abandoned in place. Subsequently, construction of the permanent generator enclosure, green space and other site work will take place and is anticipated to take approximately three months once commissioning is completed. Project completion is anticipated by second quarter of 2026.


PROJECT BACKGROUND

Located at Eighth Street at Coronado Avenue, the existing Parker Pump Station was constructed in 1983 and services both storm water and wastewater flows. The new Parker Pump Station will replace the current aging and failing station. The Parker Pump Station is a critical piece of infrastructure responsible for collecting storm water from 150 acres and discharging the flow to the North Beach outfall along with collecting sanitary sewer flows in the Country Club area and routing these flows to the sewer main along Alameda Boulevard.. The replacement project will completely rebuild the Parker Pump Station to provide service for generations and better protect the pump station from impacts from flooding and storm surge.


Rendering of new Parker Pump Station

PROJECT DETAILS

  • Provide a permanent generator onsite to strengthen the reliability of the station during power outages.

  • Isolate the sanitary sewer and storm water underground structures to minimize the risk of comingled flows.

  • Construct all electrical components above ground and housed in a new Controls Building the eliminate the risk of compromising the equipment to flooding should a significant rain event occur.

  • Reconfiguration of the site to provide approximately 6,000 square feet of publicly accessible green space.

  • Relocation of all planned above-ground structures to approximately 75 feet behind the face of curb along Coronado Avenue.

  • Significantly reduce the need for a temporary, above-ground storm water and wastewater bypass system during construction by keeping the existing pump station operational throughout construction of the new station.
  • Project Status as of November 17, 2021

    Share Project Status as of November 17, 2021 on Facebook Share Project Status as of November 17, 2021 on X (formerly Twitter) Share Project Status as of November 17, 2021 on Linkedin Email Project Status as of November 17, 2021 link

    The project is currently in the 50% design phase and will be taken to the City’s Design Review Commission, currently scheduled for Dec. 8. The application, which includes architectural and landscape plans, renderings and a material board, can be viewed on this page in the Documents section on the right. The City encourages the public to review the design and provide feedback prior to the Design Review Commission meeting. However, the public also may attend the Design Review Commission meeting and provide input on the design.

    The project is currently in the 50% design phase and will be taken to the City’s Design Review Commission, currently scheduled for Dec. 8. The application, which includes architectural and landscape plans, renderings and a material board, can be viewed on this page in the Documents section on the right. The City encourages the public to review the design and provide feedback prior to the Design Review Commission meeting. However, the public also may attend the Design Review Commission meeting and provide input on the design.