Share Project update March 13, 2026 on Facebook
Share Project update March 13, 2026 on Linkedin
Email Project update March 13, 2026 link
Testing of the new pump station has begun this week with the contractor performing witness loop checks for all the new field instruments to verify the wiring is correct and the system is functional. Once this is completed the pre-demonstration testing will continue with the motor control center, program logic controller, switchboard, valves and pumps.
This testing will continue through the month and once the pre-demonstration phase has passed, the contractor will continue to the demonstration phase to test the facility using a recirculation system to route the water to test each pump.



Share Project Update February 20, 2026 on Facebook
Share Project Update February 20, 2026 on Linkedin
Email Project Update February 20, 2026 link
TEMPORARY POWER OUTAGE TUESDAY, FEBRUARY 24; 8AM – 11AM
Work continues towards startup and testing of the new pump station. The next critical-path step towards startup is the upsizing of an existing SDG&E electrical transformer and the upgrade/changing of fuses on two utility poles. Today, the City was notified by SDG&E that this work has been scheduled to take place on Tuesday, February 24. In order for this work to be completed SDG&E will need to temporarily turn off the power to the transformer and utility poles which will also affect homes along the west side of the 600, 700, and 800 blocks of Coronado Avenue. The work and associated power loss is scheduled to take place from 8:00am to 11:00am. SDG&E will be notifying affected homes via door-hangers. We apologize for this inconvenience.

Share Project Update January 12, 2026 on Facebook
Share Project Update January 12, 2026 on Linkedin
Email Project Update January 12, 2026 link
Share Project Update November 21, 2025 on Facebook
Share Project Update November 21, 2025 on Linkedin
Email Project Update November 21, 2025 link
Construction has been progressing with the new pump station. The contractor has installed most of the discharge piping, pump guide rails and associated bracing. The hydrostatic testing for the new forcemains and discharge piping has begun with the first test successful for the piping connected to the 54-inch storm water forcemain. The electrical subcontractor is continuing with the electrical and control wiring.


Share Project Update August 8, 2025 on Facebook
Share Project Update August 8, 2025 on Linkedin
Email Project Update August 8, 2025 link
This week, the Parker Pump Station Replacement Project reached a major milestone with the installation of sewer and storm water pumps for the new stations. The upgrade includes seven storm water pumps of various sizes and two sewer pumps. Crews are now working on wiring to connect the pumps and valves to the motor control center in the new Control Building. Over the next few weeks, mechanical work will continue with the installation of discharge piping.




Share Project Update January 24, 2025 on Facebook
Share Project Update January 24, 2025 on Linkedin
Email Project Update January 24, 2025 link
Construction on the new Parker Pump Station to modernize and improve the stormwater and wastewater management in the Country Club area continues.
Filanc has completed the installation of the new 48-inch storm drain pipe along with the modifications to the existing storm drain cleanout. Work on the storm water discharge piping continues and should be completed this week. The activities related to bringing in power for the new station are currently on hold as it is with SDG&E for scheduling. The crews are also working on installing the reinforcement for the storm water pump pedestals inside the new storm wet well structure.




Share Project Update December 13, 2024 on Facebook
Share Project Update December 13, 2024 on Linkedin
Email Project Update December 13, 2024 link
The contractor, Filanc continues to move forward with construction and has begun work associated with bringing in power to the new pump station; these activities include pouring a concrete pad for the new switchgear, installation of new conduits, SDG&E trench inspections, third party testing of the new equipment, and coordinating with SDG&E for the installation of a new transformer. Work also continues on the installation of the new 48-inch storm drainpipe, modifications to an existing storm drain cleanout, and laying the storm water discharge piping.



Share Project Update: Nov 12, 2024 on Facebook
Share Project Update: Nov 12, 2024 on Linkedin
Email Project Update: Nov 12, 2024 link
Crews continue with the construction of the new underground pump station structure with placing rebar and laying out hatches in preparation of pouring the deck of the new storm water wet well and valve vaults. This will complete the major structural work for these structures. In addition, utility work in Coronado Avenue is underway with installation of the new 48-inch storm drainpipe. Crews will also install the force main piping at the rear of the new pump station in the coming weeks, and with the completion of this work, the construction of the new Controls Building can begin.
The Contractor has been maintaining the Best Management Practices (BMPs) onsite, and preparations have been made for anticipated rain events; this includes street sweeping and removing the inlet protection, allowing runoff to enter the storm drain system. The City has staged two dedicated, portable sewer bypass pumps at the station. One is already connected for an efficient start up, should it be needed, and a second is at the station for redundancy. A generator is ready to be powered up if there is an electrical outage. Other portable pumps are available for use around town. Additionally, we have spare sewer and storm wet well parts on-hand and the pump station alarms have been verified. During a major storm event, residents can stay up to date by checking the City website or social media sites.




Share Project Update: August 9, 2024 on Facebook
Share Project Update: August 9, 2024 on Linkedin
Email Project Update: August 9, 2024 link
Construction continues on the Parker Pump Station project. Large excavation is taking place, and a new 48-inch storm drainpipe is being installed on the new trash rack structure. Crews have excavated the area to the west of the new storm drain wet well, in order to construct a valve vault structure. Utility installation has also started along Coronado Avenue. This work involves constructing new sewer and storm drainpipe and manholes.
The intersection closure at Coronado Avenue and Eighth Street remains in effect with an anticipated reopening in spring, 2025. This will allow the street work to be completed and will keep pedestrians and vehicles safe around the work zone.

Share Project Update: May 31, 2024 on Facebook
Share Project Update: May 31, 2024 on Linkedin
Email Project Update: May 31, 2024 link
The construction on the new Parker Pump Station at Eighth Street and Coronado Avenue is progressing. Recently, the walls for the new storm water trash rack structure were poured and the City contractor is installing the interior walls and the pump pedestals inside the storm water wet well.
Ongoing work is progressing on the waterproofing of the new pump station structures and backfilling the large excavation. Once completed, the Parker Pump Station will improve operational efficiency and prevent flooding in homes and stormwater.

